The Data Centers LLC v. 1743 Holdings LLC, C.A. N15C-02-041-EMD CCLD (October 27, 2015)
This interesting decision upholds a claim based on the alleged duty to negotiate a contract in good faith. This confirms the need to be careful in wording letters of intent or you may be obligated for more than you were willing to give.